Bring on the insulation, WE PASSED INSPECTION!  Today we passed our big combo inspection for rough electrical, plumbing and framing.  With spring break looming we wanted to be ready to put in some full days on the house and make some real progress.  Dave was great, he came over a bunch to help us be sure we were ready.   


 Last week we had the second subpanel installed.  This is where all of the addition will be powered from.
 Last week Idyllwild Heating also came over and roughed in our new ducting.
 Through it all the girls made sure the view was still good.
Our hope is to get all of the insulation in by next Thursday for another inspection.  If we pass then we can start in on drywall and t&g pine.  Fingers crossed.